Before you order a shed kit or book a build, it helps to know how big you can go without dealing with the building department. The short answer on the size of shed you can build without a permit in Ontario is 15 square metres, or about 161 square feet. That only holds if the shed meets a few other conditions, and your municipality's zoning rules apply either way.
Below is what the Building Code says and what three Durham Region municipalities add on top. This isn't legal advice, and rules change. Confirm with your municipality's building department before you build.
Shed Size Without a Permit in Ontario: The 15 Square Metre Rule
Ontario's current Building Code is the 2024 edition, which came into effect on January 1, 2025. It exempts a shed from the building permit requirement, but only if all five of these are true. The shed:
- is no more than 15 square metres in gross area
- is no more than one storey tall
- isn't attached to a building or any other structure
- is used only for storage that goes with the main building on the lot, which is usually your house
- has no plumbing
How to Measure Your Shed
The Code measures gross area between the outside surfaces of the exterior walls, and it counts every floor above grade. So go by the outside wall dimensions, not the floor space inside or the size in the product name.
Here's how a few common sizes compare with the limit:
- 10 x 16 feet is 160 square feet, about 14.9 square metres. It's under, but with almost no room to spare.
- 12 x 12 feet is 144 square feet, about 13.4 square metres
- 12 x 14 feet is 168 square feet, about 15.6 square metres, which is over
What Takes a Shed Out of the Exemption
Any one of these means the shed exemption no longer applies:
- Using it for anything other than storage. A playhouse, a sauna or a hobby room isn't a storage shed, and Whitby and Oshawa both require a permit for other accessory buildings over 10 square metres (about 107 square feet).
- Any plumbing, even a single sink
- Attaching it to the house, the garage, a deck, a fence or any other structure
- Adding a second storey
Zoning Rules Still Apply
Skipping the building permit doesn't mean the shed can go anywhere. Your municipality's zoning bylaw sets how close it can be to your lot lines, how tall it can be, how much of the lot accessory buildings can cover and how many you can have. Those numbers aren't the same everywhere.
Here's what three municipalities in our area say on their own websites. These are short summaries, not the full bylaws, and corner lots in Oshawa and Whitby have extra setbacks.
- Clarington (Bowmanville, Courtice and Newcastle): The Municipality's accessory structures page says you need a building permit for all construction over 10 square metres (107 square feet). Setbacks, floor area and height limits vary between urban and rural areas, and Clarington asks you to contact its Building Services Division before you start.
- Oshawa: In most residential zones, accessory buildings have to sit at least 0.6 m (2 feet) from the interior side and rear lot lines and are generally limited to 4.5 m (14 feet 9 inches) in height. Together, they can't cover more than 10% of the lot, the footprint of the house or 60 square metres, whichever is smallest. Oshawa's page also says a new shed or garage on a concrete foundation needs a site alteration permit.
- Whitby: Accessory structures in residential zones can only go in a side or back yard, at least 0.6 m from any interior or rear lot line. Eaves and overhangs can reach up to 0.3 m into that setback. Height is generally capped at 4.5 m, and windows that face a neighbour or the street can mean a bigger setback.
Before You Dig: Locates, Easements and the Base
Even a gravel pad means digging. Ontario Dig Authority, formerly Ontario One Call, says any project that breaks ground needs locates, no matter how small or shallow. Locates are free. Submit your request through Ontario Dig Authority's online portal at least 5 business days before you dig, and call 1-800-400-2255 if you have questions.
Find out where any easements run and where the septic system is, if you have one. Clarington's permit drawings ask you to mark easements, rights-of-way and septic systems, and Oshawa's ask how far the shed will be from them. That's useful to know even when no permit is needed.
Then there's the base. Blocks set straight on the soil can shift as the ground freezes and thaws, and a shed in a low spot can end up sitting in water each spring. We set sheds on a level base that lets water drain away, well clear of the spot the yard drains toward.
Getting Your Shed Built
Pedro has 16 years in construction behind him, 15 of them as a Home Inspector. We build sheds on proper footings with level framing. If your shed needs a permit, we'll tell you at the start and can coordinate with your municipality. A basic shed usually runs $2,000 to $5,000 and typically takes us 3 to 5 days.
Late fall and winter are a good time to settle the size and the spot, so the build can start in spring. Wherever you live, Kawartha Lakes and Northumberland County included, check with your own municipality before you build, since bylaws get updated. Then call us at (289) 928-5689 for a free written estimate.